Circular
nrnayak/paradeep/iffco
Created: 18/12/2019 11:01
IFFCO-Paradeep


Circular Title:

Cloud WLS VM Migration on Oracle Data Center at Mumbai*

Deptt./Section:

System* Never Expired : Yes

We have received the following communication from HO. Application softwares running in cloud will remain down from 19/12/2019 , 9.00 PM to 20/12/2019, 6.15 AM . Major affected softwares are Production Reporting System , Lab Analysis System etc. ERP, HRMS , PHAST & other softwares will remain normal. E-mail & Internet will remain normal. for kind info to all concerned pls.

Regs
N R Nayak
DGM(IT Services)



As informed earlier, Oracle team has started the process of migration from OCI-Classic to OCI at Mumbai. Please find bellow schedule for migration of Windows VM (WLS instance). During migration, Weblogic services will be down as per schedule below. Post migration, Shri Shivendu will ensure availability of the WLS services. Please communicate to the users accordingly.

Plant
Date
Start Time
Pre-Req Complete time
Migration start Time
Approximate End Time
End Time
VM Creation
VM Migration status
Kalol18th Dec
9:00 PM
10:15 PM
10:15 PM
6:15 AM
Paradeep19th Dec
9:00 PM
10:15 PM
10:15 PM
6:15 AM
Aonla20th Dec
9:00 PM
10:15 PM
10:15 PM
6:15 AM
Phulpur21stDec
9:00 PM
10:15 PM
10:15 PM
6:15 AM
Kandla22nd Dec
9:00 PM
10:15 PM
10:15 PM
6:15 AM


With Regards,

Sanjay Kumar
Dy General Manager (I.T.Services)
IFFCO SADAN, C-1, District Center, Saket Place
New Delhi - 110017
011-26542846